Test Freeze (End of Increment 5)
Milestone
If applicable: code updates and fixes on short notice are completed (based on INT Test findings).
Code Version
- Code version to enter E2E-Test-Phase is clearly identified.
- FOSS best case: released in Tractus-X.
- All relevant and active TRGs are fulfilled for deployment to INT environment.
- A released product Helm-Chart is available.
Testing
- Unit-Tests and/or Tests at the end of a Sprint are successfully completed and results documented.
Timeline
- 1 day