Feature Freeze / Kick-Off E2E Test (mid of Increment 5)
Milestone
No further development of features and functions.
- Committed content for the current CX Release package shall be available.
- Any deviations must be documented and communicated, especially items not covered or incomplete.
Code Version
- FOSS: tagged at least / best case: released in Tractus-X.
- All relevant and active TRGs are fulfilled for deployment.
- A released product Helm-Chart is available.
Testing
- Unit-Tests and/or Tests at the end of a Sprint are successfully completed and results documented.
Timeline
- 1 day