Release Freeze (End of Increment 6)
Milestone
No further functional code changes for the current CX Release.
Code Version
- The tested code-version for the current CX Release is final.
- FOSS released in Tractus-X, including Release Notes (changelog.md) and documentation.
- Any verifications (for example final SEC scans) will refer and be based on this version.
E2E Tests
- E2E tests completed.
- Either completely successful.
- Or all relevant bugs have been fixed and successfully tested afterward.
- Loops and bugfixes and accepted in E2E test phase - between E2E test start and release freeze milestone - orchestrated by central Test Management.
- Results documented.
Timeslot between Release Freeze milestone and E2E Test end
- Finalization of E2E tests is ok (including repeated or regression-tests).
- There is no more bugfixing for the current Release (code is final).
- Positive test results will be documented in the final overall test report.
- Negative or incomplete results have to be documented as "known knowns" for the current Release in the Release Notes (decide on a case-by-case basis if documentation on product level or within Overarching Release Note is appropriate).
Timeline
- 1 day