Feature Freeze / Kick-Off E2E Test (mid of Increment 5)

Milestone

No further development of features and functions.

  • Committed content for the current CX Release package shall be available.
  • Any deviations must be documented and communicated, especially items not covered or incomplete.

Code Version

  • FOSS: tagged at least / best case: released in Tractus-X.
  • All relevant and active TRGs are fulfilled for deployment.
  • A released product Helm-Chart is available.

Testing

  • Unit-Tests and/or Tests at the end of a Sprint are successfully completed and results documented.

Timeline

  • 1 day